DEFINITION:
When an employee enters time on a specific project it is known as charging efforts of the employee on the project for a given time frame. This time further has some cost defined to calculate the actual cost incurred by the employees on the project.
The calculation process of the raw cost for such labor/time entered is called as Labor Cost.
The time can be entered via a third party tool or via the PA pre approved batch.
To initiate the process of cost calculation, there are few setups to be created at OU level.
Pre requisite setups to initiate time entry.
  1. Implementation option to be defined in the costing tab.
1
The option “ Interface Employee Labor Costs” is enabled, the labor cost lines accounting is interfaced to GL.
2.    Rate schedule to be defined for cost rates.
Cost Rate: The cost rates is the basic cost defined at the employee or job level in the functional currency. This is the cost used to calculate or derive the raw cost for each expenditure item of type labor/time.
Note: For time the Unit of measure is always hours.
To define the rate schedule,
Navigation: Setup->Expenditure Rate Schedule.
Calculation:
Example: cost rate = 100 USD time entered for a day = 8 hours.
Raw Cost = Quantity X cost rate, hence raw cost would be 100USD X8 hours.
3.    Cost rate schedule to be assigned at the OU level.
Navigation: Setup->Costing->Labor->Oraganization Labor Costing Rules

4. Transaction source definition for time entry.
Navigation: Setup->Expenditure->Transaction Sources
5
4
Note: In an organization when a third party tool is used by employees to enter time, a customized transaction source can be defined for same.
 There are various functionalities available for treating the expenditure items created via the transaction source.
Few of them used in common are as follows:
  1. Purge After Import: The expenditure item once created will be automatically purged from the PA interface table.
  2. Allow Reversals: The expenditure items/batches created via the source can be reversed in PA.
  3. Adjustments: The expenditure items created via the source can be adjusted in PA.
Note: The other can be enabled as per the business requirements.
Once the above setups are created, we shall now see how to enter time for a project via a pre approved batch.
Step1: The entry of time via a pre approved batch
Navigation: PA responsibility -> Expenditure -> Pre Approved Batch
6
In the form, we need to enter the OU, batch name, ending date & class. We shall create the batch for time entry.
Click on Expenditure Items: Enter employee details.
It will take you in the below section of the form where we need to enter the date of the expenditure (expenditure item date), project code, task code and the expenditure type and quantity.
Note1 : The project should be in approved status, employee should be assigned to the same OU in which we are entering time.
Note2: When we have employees entering time on projects from other OU of different LE it is included in the ICB scope and if time entered in different OUs within same LE it is included in Borrowed And Lent Functionality Scope.
Step2: Pre Approved Batch To Be Released
Once the time has been entered the pre approved batch needs to be in status “Released” for the further costing process.
Note1: There are three statuses in the preapproved batch
Working: The transaction is being entered and the batch is still open for making changes.
Submitted: The batch has been eligible for the next process of being released, however if more changes are required, the button “Working” can be clicked to make changes as required in the same form.
Released: Once the batch is in submitted status it is eligible for getting released.
Once a batch has been released no changes will be allowed to the batch (the working button is disabled).
If changes are required in the batch at this stage the batch can be reversed.
Note2 The batches with released status is eligible for cost distribution.
Step3: Cost Distribution Process:
The new expenditure items are created and now in the cost distribution process, the raw cost (also known as basic cost in PA) has to calculated.
The newly/existing expenditure items can be viewed from the below screen.
Navigation: Expenditure->Expenditure Inquiry-> Project.
Process to calculate the cost: Execute the following program to distribute cost and interface to GL.
A streamline process “PRC: Submit Interface Streamline Processes” with parameter DXL can be executed.(DXL = Distribute labor cost and interface to GL)
The streamline process calls for the following program:
PRC: Distribute Labor Costs (The program distributes cost for all the eligible expenditure items. The cost distributed flag is checked when cost distribution flag is successfully distributed.)
PRC: Generate Cost Accounting Events (The cost events is created for process “Labor Cost“)
PRC: Create Accounting (The accounting is generated)
Accounting Program
Journal Import (Journal is imported in GL)
Posting: Single Ledger
Update Subledger Accounting Balances
Note: The above programs can be executed as single concurrent programs as well.
PRC: Distribute Labor Costs (The program distributes cost for all the eligible expenditure items. The cost distributed flag is checked when cost distribution flag is successfully distributed.)
PRC: Generate Cost Accounting Events (The cost events is created for process “Labor Cost“)
PRC: Create Accounting (The accounting is generated and interfaced to GL, posting also done if the parameter Post To GL = Yes )
In the expenditure inquiry window we can query the project and check the expenditure items entered and the cost generated for the expenditure items in the column “Project Functional Raw Cost”.
Note: Once the cost distribution has been completed successfully the cost distributed flag is auto checked by the system for the expenditure item ids. The further process ie, revenue is generated only if this cost distributed flag has been checked ie the billable expenditure items are eligible for revenue and invoice process if the cost distribution has been completed.
Note: To check additional fields in the expenditure item window, we can select it from
toolbar-> folder->show field-> cost distributed & billable fields to check the status.
Note: The non billable expenditure items incur only cost, no revenue or invoice process required for non billable items.
Cost Override:
In cases where we need the cost calculation at a different rate then the cost rate defined in the rate schedule the cost override functionality can be used.
Navigation: PA Responsibility->Setup->Costing->Labor->Labor Costing Overrides.
7
8
Enter the costing rule, override type, rate & currency. The rates would be applicable for the period as per the start and end date defined for the employee.
Thanks.

Comments

Popular posts from this blog

O2C Cycle with Accounting Entries

  ORDER    TO  CASH  PARTICULARS  DR  CR SPL NOTES ACCOUNT IS PULLED FROM Sales order entry No Accounting Sales Order Pick From Sub Inventory A/c 100 At Standard Cost Sub-inventory Material A/c Setup To Sub Inventory A/c 100 At Standard Cost(Staging) Sub-inventory Material A/c Setup Sales Order Issue COGS 100 It can be fetched from five places Master Item/Org/Order Type/Line Type/Shipping Params To Sub Inventory A/c 100 At Standard Cost Sub-inventory Material A/c Setup Transaction level Receivable A/c 120 Auto Accounting Tax A/c 10 Auto Accounting Freight A/c 10 Auto Accounting Revenue A/c 100 Auto Accounting Receipts Receipts with no remittance method Cash 100 Before application of the receipt Receipt class Unapplied A/c 100 Receipt class Unapplied A/c 100 After application of the receipt to the transaction Receipt class Receivables A/c 100 Receipt class Cash A/c 100 Receipt class Unidentified A/c 100 In case of receipt without customer...

Oracle Subledger Accounting (SLA) Tables, Views

Oracle Subledger Accounting (SLA) Tables, Views Oracle Subledger Accounting Tables: TABLE NAME DESCRIPTION XLA_AAD_GROUPS The XLA_AAD_GROUPS table stores the merge dependencies analyzed during the merge analysis.  All application accounting definitions with the same GROUP_NUM must be merged together. XLA_AAD_HDR_ACCT_ATTRS The XLA_AAD_HDR_ACCT_ATTRS stores standard, system and custom sources assigned to an accounting attribute at the AAD level. XLA_AAD_HEADER_AC_ASSGNS Store the analytical criteria for the application accounting definitions. XLA_AAD_LINE_DEFN_ASSGNS This table stores the journal lines definitions for the application accounting definitions. XLA_AAD_LOADER_DEFNS_T The XLA_AAD_LOADER_DEFNS_T table is the interface table that facilitates the data transfer from data files and the database. XLA_AAD_LOADER_LOGS The XLA_AAD_LOADER_LOGS table stores the errors and logs generated by the application accounting definitions loader. XLA_AAD_SOURCES XLA_AAD_SOURCES table stores a...

Number to Word conversion in RTF

<?xdofx: expression ?> for extended SQL functions <?xdoxslt: expression ?> for extended XSL functions. You cannot mix xdofx statements with XSL expressions in the same context This function enables the conversion of numbers to words for RTF template output. This is a common requirement for check printing. The new function is “to_check_number”. The syntax of this function is <?xdofx:to_check_number(amount, precisionOrCurrency, caseType, decimalStyle)?> The following table describes the function attributes:   Attribute Description Valid Value amount The number to be transformed. Any number precisionOrCurrency For this attribute you can specify either the precision, which is the number of digits after the decimal point; or the currency code, which will govern the number of digits after the decimal point. The currency code does not generate a currency symbol in the output. An integer, such as 2; or a currency code, such as ‘USD’. caseType The case type of th...